Nuclear
Pit Facility's Merits, Snags, and Timelines
January 2005, page 12
In the June 2004 issue of Physics Today (page
34), Jim Dawson reports on the American
Physical Society (APS) discussion paper, published
in April 2004, about a modern pit facility. That paper
evaluates an MPF based on an overly optimistic combination
of assumptions that obviate the need for planning
such a facility. A parametric evaluation of the stockpile
plan recently delivered to Congress and the current
estimates of pit lifetimes by the National Nuclear
Security Administration weapon laboratories show that
continuous planning for an MPF is prudent risk management
to meet national security needs.1
The NNSA advocates managing the risks to national
security by uninterrupted planning for an MPF while
obtaining further information for acquisition decisions.
For example, initial results from accelerated pit-aging
experiments and from the inevitable aging effects
of plutonium on weapon performance are expected in
2007. The APS position paper advocates a high-risk
approach of deferring or curtailing the MPF project
until such information is available. The NNSA plan
for an MPF includes a series of major system-acquisition
critical decisions in 2007, in 2009, and at the start
of construction in 2012. Based on the current plan,
the Secretary of Energy will not be making irreversible
decisions on constructing an MPF until early in the
next decade. That is well beyond the 2006 minimum
date suggested by the APS position paper for making
such decisions.
The APS paper is replete with examples of unrealistic
optimism and factual errors. Some examples include
discounting the challenges of upgrading production
capacity to 80 pits per year at the Los Alamos National
Laboratory TA-55 facility or rapidly enhancing production
outputs in a future facility. Although a small capacity
of 125 pits per year is the most likely path forward,
the MPF environmental impact statement provides analyses
for capacities of 125 to 450 pits per year, not because
of a desire to maintain large stocks of undeployed
warheads as suggested by the APS paper, but to ensure
that the maximum potential environmental impacts of
an MPF have been considered for National Environmental
Policy Act compliance purposes. APS asserts that pits
in storage at the Pantex plant in Amarillo, Texas,
could be used as replacements and thus obviate the
need for a new facility. However, that assertion lacks
technical foundation because pits stored at Pantex
will age similarly to pits that are stockpiled.
Deferral of MPF planning, which was suggested in
the APS paper, would negatively affect plans for a
responsive pit manufacturing infrastructure that may
be pivotal to further reducing the number of stockpile
warheads—a cost-saving move for the nation.
Similarly, the capability to manufacture replacement
pits eliminates weapon-performance uncertainties that
result from plutonium aging and is consistent with
maintaining the moratorium on nuclear testing.
Current plans afford numerous review opportunities
until early in the next decade. National security
for the US should be based on a prudent assessment
of risks and not the overly optimistic and unrealistic
evaluation contained in the APS position paper. Early
planning and development are essential to avoid cost
overruns and delays.
Reference
1. US Department of Energy, National Nuclear
Security Administration, Report to Congressional Defense
Committees on "An Enhanced Schedule for the Modern
Pit Facility", February 2004. Available at http://www.fcnl.org/pdfs/nuc_mpfreport.pdf.
Everet Beckner
National Nuclear Security Administration
Washington, DC
Dawson replies: For comment, we contacted
Steve Fetter, chair of the national security subcommittee
of the APS Panel on Public Affairs, and Frank von
Hippel, POPA's chair.
Fetter and von Hippel comment: Everet Beckner,
the National Nuclear Security Administration's deputy
administrator for defense programs, addresses the
issues of manufacturing capacity and pit longevity.
The starting point for APS's Panel on Public Affairs
(POPA) discussion paper The Modern Pit Facility1
was NNSA's June 2003 draft environmental impact statement
(EIS) on the proposed construction of a modern pit
facility.2
The draft EIS specified an MPF with a single-shift
production capacity of up to 450 plutonium pits per
year and a construction schedule that assumed that
the pits currently in the US stockpile will need replacement
when they are 45 years old.
The APS panel questioned those assumptions and actively
sought appropriate input. NNSA-supported scientists
contributed significantly to our analysis and NNSA
officials had draft copies of our report in October
2003. The report then underwent the APS approval process,
while NNSA revised its analysis. In its February 2004
report to Congress, NNSA lowered the MPF base production
capacity to 125 pits per year and raised the assumed
pit longevity to 60 years. NNSA changed its capacity
and longevity assumptions in a manner consistent with
the POPA report.
Beckner also criticizes the POPA recommendation
for an outside feasibility study of increasing the
capacity of the existing pilot pit production line
in the TA-55 facility at Los Alamos National Laboratory.
We made that recommendation because NNSA has backed
away, without adequate explanation, from its own estimate
that the single-shift production capacity at TA-55
could be increased to 50–80 pits per year and,
with an added wing, to 150 pits per year.
Perhaps the most important contribution of the POPA
paper was to point out that, although a production
facility is necessary, its requirements need careful
reexamination, and the possibility of early production
of pits at TA-55 offers considerable leverage. Congress
recently suspended fiscal year 2005 funding for MPF
site selection and requested a report on production
requirements. That wise course of action is recognition
that the need for an MFP is not urgent and there is
adequate time to explore key science issues relating
to pit longevity.
2. US Department of Energy, National Nuclear Security
Administration, Modern Pit Facility Draft Environmental
Impact Statement, NNSA, Washington, DC (4 June
2003). Available at http://www.mpfeis.com.